Site Plan Review: What Happens After You Submit

Quick answer

Site plan review is the stage where a city employee checks your drawing against the zoning rules before a permit is issued. For a residential deck, fence, shed, patio or garage it is usually a desk check by one or two reviewers, not a public hearing. Across the 985 city records we track that publish a timeline, the median upper bound is 14 days, and 96% land within a month. It ends one of two ways: the permit is issued, or you get a numbered list of comments to fix. The second one is normal and is not a rejection.

You submitted the drawing. Now nothing is happening, the portal says "in review," and nobody has told you what that means or how long it lasts. This page is the inside of that black box.

One disambiguation first, because it is the reason this term is so confusing to search for.

Two different things are called "site plan review"

The phrase means two genuinely different processes, and most of what you will find online describes the one you are almost certainly not in:

If your project is a backyard structure on an existing single-family lot, you are in the second process. Reading the first one's timeline and getting frightened is one of the more common ways homeowners talk themselves out of pulling a permit.

Who actually reads your drawing

More than one desk usually touches it, which is why review takes days rather than minutes:

Each of these is a queue, and they are often sequential rather than parallel. That is the single biggest reason a two-minute check takes two weeks.

How long site plan review takes

From the review timelines published by the cities behind our state guides, 985 city and project records with a stated turnaround:

Published review time Share of tracked records
One week or less 9%
One to two weeks 44%
Two to four weeks 43%
One to two months 4%
More than two months under 1%

The median upper bound is 14 days, and 96% of tracked records land within a month. By project, patios are the slowest of the four we can measure at about 20 days at the median upper bound, because covered patios pull structural review in behind the zoning check; decks, sheds and garages sit around 14 to 15 days.

Two caveats worth holding onto. These are the timelines cities publish, and a published timeline is a target rather than a promise. And the clock in most departments starts at acceptance, not at submission, so a package that sits three days at intake for a missing document has not started its two weeks yet.

Your own city's figure is in the permit cost calculator alongside its fee.

What the reviewer is actually checking

It reads like a short list. It is not. Each line below is several separate checks, and each one has its own way of failing:

The real difficulty is not the list. It is that the legally meaningful content, your boundary dimensions and your easements, does not exist anywhere on your property. It has to be pulled from county records and reconciled against what the aerial shows, and a few feet of error in that step is exactly the size of the setback being measured.

Our drafters run a longer version of this before any plan leaves the shop. The pre-submission checklist publishes the reader's version, seven checks you can hold any drawing to, ours or your own. What happens internally goes further: the parcel outline is reconciled against the dimensions on your recorded plat rather than trusted from GIS alone, easements are drawn from the recorded documents rather than from what is visible on the ground, every setback is dimensioned from the nearest projecting point, and the scale is verified across the whole sheet rather than assumed from the software. All seven checks arrive done, the submission format included, so the plan is ready to upload rather than ready to reformat.

That is the difference between a drawing that looks right and one that survives a reviewer, and it is why 98% of the plans we deliver clear review with no correction notice at all, with revisions free until your building department accepts the drawing.

What comes back, and what it means

Review ends in one of three outcomes:

  1. Approved. The permit is issued, usually with conditions printed on it and an inspection schedule attached.
  2. Approved with corrections, or comments to address. A numbered list of what to change. Your application stays alive, you fix the items, and you resubmit into a recheck queue that normally moves faster than the first review because only the flagged items get re-read.
  3. Denied. Rare on residential accessory structures, and it means the project conflicts with a rule that redrawing cannot fix, almost always a zoning conflict rather than a drafting problem.

Outcome 2 is by far the most common non-approval, and homeowners routinely read it as outcome 3. If a letter has landed and you are not sure which one you got, what to do when a building permit is rejected reads the letter with you.

Five things that make review go faster

  1. Submit a complete package the first time. Intake bounces cost days and do not start the review clock.
  2. Label every setback with a number. The most common single comment, and entirely preventable.
  3. Pull your recorded plat before you draw. Easements are invisible in the yard and are the correction most likely to force a redesign rather than a redraw.
  4. Match the submission format. Many departments want a single flattened PDF at a stated sheet size. A drawing that is correct but formatted wrong can still bounce at intake.
  5. Answer comments completely and in one pass. Partial responses guarantee another cycle, and some departments start billing hourly after the second or third review.

Across everything we deliver, 98% of plans clear review with no correction notice at all, and the ones that do come back are typically accepted within days of the fix.

If you would rather not gamble on it

A permit-ready site plan is $89 to $259, delivered in 24 to 48 hours, drawn to scale from county GIS records and satellite imagery with setbacks dimensioned, existing structures shown and easements of record included. If a reviewer does comment on it, revisions are free until your building department accepts the drawing.

Drawing it yourself is a legitimate route for a simple lot. The six-step walkthrough covers the method, the blank site plan template gives you a permit-formatted sheet to work on, and the complete guide covers every element in more depth.

Frequently asked questions

How long does site plan review take?

Across the 985 city and project records we track that publish a turnaround, the median upper bound is 14 days and 96% land within a month. Nine percent of tracked records promise a week or less, 44% one to two weeks, and 43% two to four weeks. Patios run slowest of the projects we can measure, at about 20 days, because covered patios pull structural review in behind the zoning check. Note that most departments start the clock when the package is accepted as complete, not when you upload it.

What is the difference between site plan review and a building permit?

Site plan review is a stage inside the permit process, not a separate approval. The reviewer checks your drawing against the zoning rules, setbacks, lot coverage, height and easements, and the building permit is what gets issued once that check and the construction plan check both pass. On a small residential project the two often happen inside the same application and you never see them as separate steps.

Does a homeowner need to attend a site plan review hearing?

Almost never for a backyard project. Hearings belong to discretionary site plan review, which applies to commercial buildings, subdivisions and multi-family development. A deck, fence, shed, patio or detached garage on an existing single-family lot gets an administrative desk check instead: a reviewer reads the drawing, applies the zoning table, and approves it or writes comments. No hearing and no public comment period.

What happens if my site plan fails review?

In most cases it did not fail. You received a correction notice, which is a numbered list of what to change before the reviewer can approve it, and your application and fee stay alive while you fix it. Correct every item in one pass and resubmit before the deadline printed on the notice; rechecks are usually faster than the first review because only the flagged items get re-read. Outright denial is rare on residential accessory structures and means a zoning conflict that redrawing cannot solve.

Can I check on my site plan review status?

Yes, and it is worth doing. Most departments now run a permit portal where you can see which desk your application is sitting at and whether comments have been issued. If there is no portal, calling the permit counter with your application number is normal and expected. Reviewers would generally rather answer a question about a comment than read the same incorrect drawing twice.

Permit requirements vary by city, county, and state. The information in this guide provides general guidance based on common building codes and practices across the US. Always verify requirements with your local building department before starting your project.